Meeting notes from February 11, 2026, were approved.
Gisele updated the committee on the progress of the following projects:
ADA Compliant Stairs/Ramp project
- This project is funded by Orsted, wind farm developer.
- Orsted mailed the check on Feb 20 and Town Hall is looking for it.
- Construction began on March 9 and is expected be complete on or before April 30.
Homestead Weatherization Project
- This project is funded by Orsted, wind farm developer.
- Funding has been received by the Town and is waiting to be spent.
- This project will use some CPA Funds as well.
- Installation of mini-splits has begun.
- Insulation work will begin once that is complete.
- Hope to be complete by April 1
Homestead Painting/Electrical/Water Project
- This project is funded through a Mass Cultural Council grant and the Aquinnah CPA.
- The well/waterline project is complete.
- The electrical work is nearly complete, with just a few loose ends to tie up once the painting is complete.
- We are working with the painting contractor to schedule the work. Can’t start until the weatherization work is complete.
Other
- Gisele also reminded the committee that she will be away on vacation, and unreachable, from Feb 24 – March 6.
Next meeting is scheduled for March 11, 2026.
Meeting adjourned at .